LINCOLN, Neb. (AP) — Nebraska's highest court tossed a lawsuit Friday challenging a proposed route for the Keystone XL oil pipeline in a decision that could remove a major roadblock for the $7 billion cross-continental project, which Republicans have vowed to make a key part of their 2015 agenda in Congress.
The lawsuit challenged a 2012 state law that allowed the governor to empower Calgary-based TransCanada to force eastern Nebraska landowners to sell their property for the project.
In a split decision, four judges on the seven-member Nebraska Supreme Court agreed that the landowners who sued the state had legal standing to bring their case. But because the case raised a constitutional question, a super-majority of five judges was needed to rule on the law.
"The legislation must stand by default," the court said in the opinion.
The proposed 1,179-mile pipeline would carry more than 800,000 barrels of crude oil a day from Canada to refineries along the Texas Gulf Coast, passing through Montana, South Dakota, Nebraska, Kansas, Nebraska and Oklahoma along the way.
The newly empowered Republican-led Congress is moving ahead on approving the project, with the House scheduled to vote on Friday. The Senate is expected to finish the bill by the end of the month, setting up a showdown with President Barack Obama, who has threatened a veto.
The pipeline needs presidential approval because it would cross the U.S.-Canada border.
Environmentalists and other opponents argue that any leaks could contaminate water supplies, and that the project would increase air pollution around refineries and harm wildlife. But the GOP, oil industry and other backers say those fears are exaggerated, and that the pipeline would create jobs and ease American dependence on oil from the Middle East. They note a U.S. State Department report raised no major environmental objections.
TransCanada has said that if the Nebraska Supreme Court invalidated its proposed route, it would reapply through the Nebraska Public Service Commission, which currently includes four Republicans and one Democrat. Members are elected by district and generally take about seven months to approve or deny an application.
Members of the commission are elected by district and generally take about seven months to approve or deny an application.
Nebraska Gov. Dave Heineman opposed TransCanada's original proposed route that crossed the environmentally sensitive Sandhills region, but he approved the project in 2012 after the company altered the pipeline's path to avoid the Sandhills. Heineman noted that the proposal was reviewed by the Department of Environmental Quality, which is part of his administration.