Phillip Gibson of Trilogy Engineering, the company hired to perform the corrosion-control study at Jackson’s two water plants, told the city council Tuesday that he had identified the source of the problems with the lime feed system.

Stories this photo appears in:

Tease photo City & County

Jackson Water: Lime Problem Went Unnoticed for Years, Fixed Now

Lead appearing in Jackson’s water in 2015 resulted from a faulty lime-feed system at O.B. Curtis Water Treatment Plant, as well as shifting water chemistries, an expert consultant told the …