The three elected commissioners said two weeks ago that Kemper should run on natural gas and not gasified lignite coal, that rates should stay level or fall, and that customers shouldn't pay for the gasifier. Last week, Mississippi Power said it was suspending efforts to complete the gasifier, which is three years behind schedule. The plant is more than $4.5 billion over budget. Photo courtesy Mississippi Power
Stories this photo appears in:
Staff: Mississippi Power Offering Ideas to Settle Kemper
The man in charge of negotiating a settlement to wind down Mississippi Power Co.'s coal-fueled power plant project says the company has already made proposals.